http://www.nepalnews.com
spotlogo2.jpg (6318 bytes) VOL. 23, NO. 47, JUNE 11 -  JUNE 17  2004 ( JESTHA 29, 2061 B.S. )
OPINION

STARTLING  PARADOXES: Upper Karnali  Project

By Dr. AB Thapa 

Here is  a foreign  consulting   firm  that gets  a  job  to  conduct  pre-feasibility   level  study  of  the 300  MW  Mini  Upper   Karnali  Project. The  consulting  firm must  have  agreed   to  do the job with the  intention  of  earning  money.   They  had  nothing  to  do  with  the  Upper   Karnali  Storage  Project   Nobody  might  have expected  from them  that  they  should  dig  into  the   Upper  Karnali  Storage  Project  and  unravel  the   truth  that  the  300 MW  Mini  Upper  Karnali   Project  and  the  4,000  MW  Upper  Karnali   Storage  Project  are  mutually  exclusive.  As  far as  the Upper Karnali Storage Project  is concerned,  any  reasonably   experienced  hydropower  engineer  would  not  have   any  hesitation  to  tell  outright  with absolute   certainty  that  this  project  is  the  best   among  the hydropower projects  identified  in  Nepal.   The  consulting  firm   must   have sensed     without  much  difficulty  that  the   government  intends to  implement  the  300 MW  Mini   Upper  Karnali  Project  in  near  future.  So   they  might  have  considered  that  it was  their   solemn  duty  to  caution  the  government  against   such  intention.  They  devoted  a  special  chapter   in the  pre-feasibility  study  report  to  explain   the  truth  that  the  4,000 MW Upper  Karnali   Storage  Project  and  the  300 MW Mini  Upper Karnali   Project  are  mutually  exclusive,  despite  the   fact  that  such  additional  reporting   was uncalled  for.  Their  message  is  very  clear.  DO   NOT  THINK OF  BUILDING  THE  300 MW  MINI  UPPER   KARNALI  PROJECT. The  relevant  excerpts  from  the   report  of  pre-feasibility  study  of  the  Upper Karnali Project  carried  out  with the assistance of  the  World   Bank  are  presented  hereinafter. 

Excerpts  from  Study   Report

The  World  Bank  supported   pre-feasibility  study  team  must  have  sensed   that our  government  could  easily  be  misled  into   deciding  to  implement  the  300 MW  Mini Upper   Karnali  Project  that  precludes  the  development of   the  Upper  Karnali  Storage Project.   As a  result,   the  study team  experts have  gone out  of  their   way  virtually to  recommend  the  government  to   throw away  the  idea  of  implementing  the  300 MW Mini  Upper Karnali  Project.  The relevant  excerpt  from   the World  Bank supported    study  report  is   presented  below  that  warns  us  about  the   dire  consequences  if  the  300 MW Mini  Upper   Karnali  Project  is  implemented.

“Even  when  assuming that   the  KR 1 A  run-of-river  project ( small  300 MW Upper   Karnali  project) is  a  sunk cost, it  will be  seen   that  a  single large  power  plant (4180 MW)  associated   with  the  major  storage  project is  less  costly   than the  combined  cost  of  smaller  plant  at   the  same  location (3532 MW)  and  a  second  power plant at  the  foot  of  the storage  dam ( 408 MW)   discharging directly  into  the KR 1A  run-of-river  project   head  pond.   Based  on  this  assessment, it   appears  that  the  later  development  of  the major   hydro  storage  project at  Site KR 1  (  mega  Upper   Karnali  Project)  would  cause  the  KR 1A   run-of-river  project  to  be  effectively  discontinued.   There  may be  limited opportunity  for  secondary  energy   generation during  the  periods of spillage”.

A  Paradigm  of   Nepal’s  Planning

It  is  often  said   that  many  developing  countries  are  unable  to   bolster  up   the  economy   at  a   reasonable  pace  not  for  want of  natural   resources  or  capital.  They  are  progressing    very  slowly  because  their  policy  makers   and  planners    posses  neither  a  clear   vision  of  their  country’s  development   perspectives  nor  the ability  and  true  dedication   to  lead  the  country  in  the  path  to   victory  over  underdevelopment  and   backwardness.   Certainly in this matter, Nepal  is  not  an  exception.   Our  country  is  also  suffering  from  the   same  type  of  ailment.  Planners  and  policy   makers  in  our  country  lack  clear  vision and   true  dedication  to  their  works,  as  evidenced   by  the  recent  government  handling  of  the   Upper Karnali  Project. 

At  present  Nepal  is   facing  upheaval  of  convincing  the international  donor   community  to  lend  annually  about  US $ 500   million  in  the  years  ahead  to  launch   development  works  to  be  taken up  to  reduce   poverty.  It  was  explained  in  the  May 7,   2004  issue  of  this  journal  SPOTLIGHT that  the 4,000 MW  Upper Karnali  Storage Project  alone  could  provide   Nepal  annually  about  US $  400  million  in royalty  to  our  country  immediately  after  the   completion of  the  project  construction,  despite  the   fact  that  this  project  is  far  smaller   than  the  Karnali  Chisapani  Project.  The  per   KW  installed  capacity  construction  cost  of  the   Upper Karnali  Storage  Project  could  be  only   about  70%  of  such  cost  of  the mammoth   Karnali  Chisapani  Project.  Apart  from such   construction  cost  advantage, the  Upper  Karnali   Project  could  generate  electricity  almost  twice as   much  as  the  project  at Chisapani  for  the same   volume of  the regulated  flow The  foreign  consultants   of  the Upper  Karnali  pre-feasibility  study had  gone   out  of  their  way to  protect  our  country’s   interest  in  ensuring  that  under  no   circumstances  the  big  hydropower  potential   of   the  Upper  Karnali  Storage  Project would  be   adversely  affected.

We  should  have  expedited   the  development  of  the  Upper  Karnali  Storage   Project  to  accrue  to  our  country  revenue   on  a  scale  far  beyond  the  expectation  of   any  of  our  planners and  policy  makers.    Such  efforts  would  have  been  greatly   helpful  in  gearing  up  to  preparing  our   country  for  the  bright  prospect  for  progress and  prosperity.  Unfortunately  to  our  great  horror   our  government  is  at  present  on  the  verge   of  deciding   to  implement  the  300  MW   Mini  Upper Karnali  Project  despite  the  fact   that  we  would  be  forfeiting  the  opportunity   to  accrue to  our  country  enormously  large  sum   in  revenue  from  the  implementation  of  the   4,000 MW Upper  Karnali  Storage  Project.  It  is   hoped  that  the  National  Planning  Commission  and   other  government  agencies  would  look  into  this   matter  seriously  before  it  is  too late. 

Why  Upper  Karnali   Site  is  Attractive

The Karnali  river makes  a   big  loop  in its  lower  reach  near  a  place   called  Asare. From here,  the  river  flows  in  the   southeast  direction  for  about  25  kilometers,   after  that  the  river  makes  a  complete   reversal  in  its  direction.  The  river  comes   back  to  a  point   just  two  kilometers   away   from  its   earlier  position  near Asare.  There  is  a  drop  of  about   150   meters  in   Karnali  riverbed  elevations  between   these  two  positions  merely   two  kilometers   away  from   one  another.  There  is  a   good site near  Asare  to  build  a  high  dam   with  a large  storage  volume.   Such  unique feature of   the  topography  on  this  stretch of  the Karnali  River makes  this  river  extremely  attractive   for a  large storage project  for  the generation  cheap peaking  power.  The  project  to  utilize  this  bend   for  power  generation  was  originally  known  as   the  Karnali  Bend  Project.  Later on,   the   name  was   changed  to   Upper  Karnali   Project.

Upper  Karnali  Storage   Project

Nepal   might  be  able   to  get  easily up to  50%  of  the  total   power  in  royalty  from  the  private  developers   if  they  are  properly  briefed  about  the   impressive  advantages  of  this  project.   By comparison with the Karnali  Chisapani  Project,  the  firm  head   of  the  Upper Karnali  Project  would  be almost   two  times  greater.  It  can  be  derived   based  on  Stage  A  Optimization  Study  Data   of   the  World  Bank financed   Karnali   Project  Study  report  that  per  KW  installed   capacity  construction  cost  of  the Upper  Karnali   Storage  Project  could  be  only  about  70%   of  such  cost  of  the  project  at  Chisapani.   It  need  not  be  explained  that  the firm   power  generation  of  the Upper  Karnali  Storage   Project  operating  at  two times  bigger   head   would  also  be  two  times  greater  from  the   use  of same  volume  of  regulated  flow  of   the  Karnali  by  comparison  with  the Karnali   Chisapani Project.  In  terms  of    energy   production  the  generation  cost  of  per  KWh   firm  energy  of  the  Upper Karnali  Project  could   be  only  about  40%  of  such  cost  of   the Karnali  Chisapani  Project.  Thus, Nepal  would  be   justified  to  require  that  the  private  developer   pay  about  50%  power  in  royalty  because   such  royalty  would  still  be  less  than  the   total  additional  generation  solely from  the  use   of  the topographical  advantage without  involving  further   investment.

The  total  generation  of   the  Upper  Karnali  Project  could  be  about   10,000 GWh.  Nepal  could  get  about  5,000GWh  in   royalty.  At present,  there  is  a  big  surge   in  demand  for  peaking  power  in  India.  The   generation  cost  of  such  power  as  explained   below  could  be  about  US Cents 12  per  KWh.   The  amount  in  royalty  from  the  developers   could  be  as  high  as  US$ 400 million  per   annum  if  it  is  assumed  that  the   electricity  would  be  sold  at  a  price  of   only  US Cents 8  per  KWh.  

Big  Surge  in Demand   for  Peaking  Power

At  present  India  is   experiencing  an  acute  shortage  of  peaking   energy. At  the  beginning  of  the  Eight  Plan,   the  total  peaking  shortage  was  20% whereas  the   energy  shortage  was  only  9%  of  the  total   power  generation.  The  thermal  and  nuclear  power   stations  are  suitable  to  supply  electricity  to   meet  the  base  load  demand  of   the   system.  It  is  not  economic  to  use  them   to  supply  peaking  energy.  Gas  turbines  can   be  used  to  meet  the  peak  load  demand   because  of  low  specific  investment  costs  and   quick  start  up.  However,  the  efficiency  is   limited   due  to  the  high  exhaust  gas   temperature  of  the  turbine.

India  is  making  every   effort  to  improve  the  hydrothermal  mix  for   ensuring  better  system  operating  condition.  However,   the  share  of  hydropower  in  the  overall   power  generating  capacity  has  steadily  declined   since  the  last  few  decades. The  share  of   the  hydropower  in  the  overall   power   generating  capacity  was  50.6%  in  1963.    But  few  years   before  it  has  come   down  to  only  25.66%.

Role  of  Rastra   Bank

It  is  said  that   nowadays  Nepal  is  receiving  annually  about    one  billion  US Dollars  equivalent  from  Nepalese   citizens  working  in  foreign  countries.  At present,   our country  is  in  the  grip  of  economic   depression.  There  is  little  economic  activity   within  the country.  Banks  are  refusing  to   accept  new  deposits.  People  are  holding  foreign   currency  either  in  cash  or  spending  it  in   buying  properties. 

In the past,  the  Rastra   Bank  had  played  avant-garde  role  in resolving   country’s  economic  problems.  Some  years  back   the APROS  was  established  under  the  aegis  of   the  Rastra  Bank  to  resolve  agriculture  related   problems  of  our  country.  Now  Rastra  Bank   should  think  of  finding  new  ways  to   utilize  the  surplus  foreign  remittance  to   bolster  up  our  country’s  economy.  Such   money  sent  by  Nepalese  citizen  working  in   foreign  countries  could  be  invested  in exceptionally   attractive  export  oriented  hydropower  projects.  The   4,000 MW  Upper Karnali  Storage  Project  estimated  to   cost  about  2,500 million  US Dollars could  be  an   ideal  project  for  such  purpose.   Shares   could  be  floated  to  raise  capital.  Nepal   could  hope  to  borrow  money  from  foreign   banks  also  against  the  guarantee  of  the   purchaser  of  electricity.  The  equity  debt  ratio   could  be  around  25%.  It  appears  quite   likely  that  there  might  be  about  30%   return  on  equity  even  after  paying  around   50%  of  the  total  amount  earned  from  the   sale  of  the  electricity  in  royalty  to  the   government. 

In  Conclusion

It  is  primarily    intended  to  draw  the  attention  of  the   concerned  Government  agencies,  various  institutions   involved  in  Nepal’s  water  resources  development   and  financial  institutions like  the Rastra  Bank    to  great  loss  to  the  nation  if  it   is  allowed  to  implement  the  300 MW  Mini   Upper  Karnali  Project.   

(Dr. Thapa writes on water resources)


Cover Story | K. Natwar Singh's VisitCongress Unification | Human Rights GuidlinesInterview | Women Migrants
Nepali Theatre | School Kids
Human Rights | Editor's Note | The Bottom Line | News Notes | Briefs | Quote Unquote
Off The Record | Letters | Opinion
| Forum | Book Review


Send your feedback to the editor: spot@mail.com.np
2004   Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 4220 773, 4243 566 . Fax: 977 1 4225 407. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on SPOTLIGHT may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to US. Send us your feedback: ABOUT US CONTACT US  HOME  
ADVERTISE WITH US

BACK TO THE TOP