![]() |
||
|
||
| OPINION |
NEA Killing
Goose Laying Golden Eggs By Dr. A.B.
Thapa At present
Nepal is facing upheaval of convincing the
international donor community to lend annually about
US $ 500 million in the years ahead to
launch development works to be taken up to
reduce poverty. It would certainly surprise us to
learn that the 4,000 MW Upper Karnali Storage Project
alone could provide Nepal annually about US $
400 million in royalty to our country
immediately after the completion of the project
construction, despite the fact that this
project is far smaller than the Karnali
Chisapani Project. It can easily be determined
that the Upper Karnali Storage Project is
certainly the best among the projects identified
so far in Nepal for the generation of
cheap peaking power. It is
explained in this brief article why the per
KW installed capacity construction cost of the
Upper Karnali Storage Project could be only
about 70% of such cost of the mammoth
Karnali Chisapani Project. Apart from such
construction cost advantage, the Upper Karnali
Project could generate electricity almost twice as
much as the project at Chisapani for the same
volume of the regulated flow. It implies that the
energy benefits to accrue from the investment made
on the Upper Karnali Project would be twice as
much as such benefits from the same
amount of investment on the Karnali Chisapani type
project. It is very painful to note
that recently planners in our country are
not seen caring to utilize our vast water
resources in the best interest of the
country. As a result, very recently the
Nepal Electricity Authority has nearly decided
to implement a small 300 MW Mini Upper Karnali
Project that would displace the Upper Karnali
Storage Project. The Upper Karnali Storage Project
and the small 300 MW Mini Upper Karnali Project
yielding very limited benefits are mutually
exclusive. Thus, the Nepal Electricity Authority is
going to kill the goose that lays the
golden eggs unless concerned agencies intervene in
time to save it. Startling
Paradoxes In Nepal, we
live in the midst of startling paradoxes.
We boast that Nepal is one of the
richest countries in the whole world in
hydropower resources, yet our people are forced
to pay electricity charge at a rate
perhaps the highest in our region. The
total annual availability of water in Nepal
might exceed our total irrigation demand
by more than four times, yet most of our
farmers are suffering for want of water to
irrigate their lands. We have it within our
power to abolish poverty and hunger, yet
we are content merely with empty rhetoric of
some of our planners. We long since
needed a new vision for development, a
vision based on true scientific facts, a
vision that will help to eradicate poverty and
underdevelopment. Unfortunately, we are failing in
our duty to provide better service to the
nation. Such failure might have resulted from
our ignorance as well as greed. The ongoing
discussions about the fate of the Upper
Karnali Storage Project is a typical example of
how even those projects which could be
the best among the projects so far
identified in our country are unfairly handled
without paying slightest attention to detailed
technical matters which would have shocked all
people if they knew the whole truth. The
Big Karnali River Loop The Karnali
river makes a big loop in its lower reach
near a place called Asare. From here, the river
flows in the south-east direction for about
25 kilometers, after that the river makes
a complete reversal in its direction. The
river comes back to a point just
two kilometers away from its earlier
position near Asare. There is a drop of
about 150 meters in Karnali riverbed
elevations between these two positions merely
two kilometers away from one another.
There is a good site near Asare to build
a high dam with a large storage volume.
Such unique feature of the topography on this
stretch of the Karnali River makes this river
extremely attractive for a large storage project for the
generation of cheap peaking power. The project to
utilize this bend for power generation was
originally known as the Karnali Bend Project.
Later on, the name was changed to
Upper Karnali Project. Study
Of The Upper Karnali Project The Karnali
basin is the first to arouse keen interest in
Nepal's vast hydropower development study. There are
several attractive sites for the generation of
cheap hydroelectric energy in this basin. In
early 1960s an agreement was signed between
HMG of Nepal and the UNDP for
providing assistance to conduct a survey of the
Karnali river and its main tributaries
culminating in a pre-investment report indicating
hydroelectric potential of the river as
well as the best sites for hydropower
development. The final feasibility report and
general basin development report were submitted
in February, 1966. In 1980s,
further studies of the two projects were
carried out under the aegis of the World Bank.
They are the feasibility study of the
Karnali Dam Project (Chisapani) and the
pre-feasibility study of the Upper Karnali
Hydroelectric Project ( Karnali Bend Site). Unfortunately,
the scope of the Upper Karnali Project
study was deliberately made very narrow.
The size of the project was scaled down
to be suitable to meet the Nepal's
internal power requirement completely disregarding
its vast potential to generate exceptionally
cheap peaking energy for export to India.
Thus, there are at present two Upper
Karnali projects. They are the 300 MW Mini
Upper Karnali Project and the 4000 MW Upper
Karnali Storage Project. These two projects are
mutually exclusive. In other words, it
would not be possible later on to build
the 4000 MW Upper Karnali Project without sacrificing
the 300 MW Mini Upper Karnali Project. Though
the Upper Karnali storage project study was
not laid in the terms of reference,
the pre-feasibility study report has clearly
warned the government about the serious
consequences if the 300 MW Mini Upper Karnali
project is implemented. The relevant excerpt
from the WORLD BANK supported Upper Karnali
project study report is presented hereinafter. World
Banks Disapproval of Mini Upper Karnali The World
Bank supported pre-feasibility study team must
have realized the great importance of the
Upper Karnali Storage Project. As a result, the
team has virtually disapproved of the 300
MW Mini Upper Karnali project. The relevant excerpt
from the World Bank supported study report
is presented below that warns us about
the dire consequences if the 300 MW Mini Upper
Karnali Project is implemented. Even
when assuming that the KR 1 A run-of-river project (
small 300 MW Upper Karnali project) is a sunk cost, it
will be seen that a single large power plant
(4180 MW) associated with the major storage project is
less costly than the combined cost of smaller
plant at the same location (3532 MW) and a
second power plant at the foot of the storage
dam ( 408 MW) discharging directly into the KR 1A
run-of-river project head pond. Based on
this assessment, it appears that the later
development of the major hydro storage project at
Site KR 1 ( mega Upper Karnali Project) would
cause the KR 1A run-of-river project to be
effectively discontinued. There may be limited opportunity
for secondary energy generation during the periods of
spillage. Royalty
from the Upper Karnali Storage Project Nepal
might be able to get easily up to 50% of
the total power in royalty from the
private developers if they are properly briefed
about the impressive advantages of this
project. By comparison with the Karnali Chisapani Project,
the firm head of the Upper Karnali Project
would be almost two times greater. It can
be derived based on Stage A Optimization
Study Data of the World Bank financed
Karnali Project Study report that per KW
installed capacity construction cost of the Upper
Karnali Storage Project could be only about
70% of such cost of the project at
Chisapani. It need not be explained that the
firm power generation of the Upper Karnali
Storage Project operating at two times bigger
head would also be two times greater from
the use of same volume of regulated flow
of the Karnali by comparison with the Karnali
Chisapani Project. In terms of energy
production the generation cost of per KWh
firm energy of the Upper Karnali Project could
be only about 40% of such cost of the
Karnali Chisapani Project. Thus, Nepal would be
justified to require that the private developer
pay about 50% power in royalty because
such royalty would still be less than the
total additional generation solely from the use
of the topographical advantage without involving further
investment. The total
generation of the Upper Karnali Project could
be about 10,000 GWh. Nepal could get about
5,000GWh in royalty. At present, there is a
big surge in demand for peaking power in
India. The generation cost of such power
as explained below could be about US Cents 12
per KWh. The amount in royalty from the
developers could be as high as US$ 400 million
per annum if it is assumed that the
electricity would be sold at a price of
only US Cents 8 per KWh. Big
Surge in Demand for Peaking Power At present
India is experiencing an acute shortage of
peaking energy. At the beginning of the Eight
Plan, the total peaking shortage was 20%
whereas the energy shortage was only 9% of
the total power generation. The thermal and
nuclear power stations are suitable to supply
electricity to meet the base load demand
of the system. It is not economic
to use them to supply peaking energy. Gas
turbines can be used to meet the peak
load demand because of low specific investment
costs and quick start up. However, the
efficiency is limited due to the high
exhaust gas temperature of the turbine. India is
making every effort to improve the hydrothermal
mix for ensuring better system operating
condition. However, the share of hydropower in
the overall power generating capacity has
steadily declined since the last few decades.
The share of the hydropower in the overall
power generating capacity was 50.6% in
1963. But few years before it has
come down to only 25.66%. Pumped
Storage Schemes Most of
the good sites for the hydropower development
have already been developed in the Northern
India. At present India is implementing even
those hydropower projects that possess unusually
difficult and challenging features and such
projects can be hardly considered
feasible even for being developed to cope
with moderate peaking demand. One of such
projects could be the 1500 MW Nathpa Jhakri project ,
which was few years back under construction in
Himanchal Pradesh. The 27.4 km long headrace tunnel
of this project , which has a diameter of 10.15 m, is said
to be one of the longest in the world. There are
even now several good sites for
hydropower development in the North-Eastern India ,
which have not yet been used. However,
such sites are at locations far away from
the load centers. As a result, the
Government of India in recent years
had to embark on a plan to
develop the pump storage schemes Pumped storage
schemes are provided for the generation of
peaking power, even though there is a net
energy loss in the system because more
energy is consumed in pumping than can be
produced by the turbines. The cycle efficiency
of a pumped storage plant can usually be
between 60 and 70 percent. It implies
that such a plant consumes about three
units of electricity to produce only two
units during the peak hours. The cost
of the peaking energy produced by a
pumped storage plant will have to take
into account the investment to be made in
the construction of the pumped storage
plant. The per unit capacity investment
cost of a pumped storage plant can be
comparable to the cost of a similar hydropower
located at a favorable site. The total per
KWh generation cost of peaking power produced
by pumped storage plant could be about US Cents
12 if it assumed that procurement price
of the thermal energy would be about US Cents
5 KWh and the operational cost of only
the pumped storage plant will be about US Cents
4.5 KWh. So far, 56
major pumped storage schemes with a total
installed capacity of 94,000 MW are reported to
have been identified in India. Already
few pumped storage schemes such as the
Nagarjun Sagar (700 MW), Kadampani (400MW), Kadana (240MW), Panchit (40MW),
Paithan, and Ujjani are either in operation
or under various stages of construction. Bids
were being evaluated some years ago by the West
Bengal authorities for a civil work contract
for the 900 MW pumped storage facilities
at Purulia on the Ayodhya hills. Three
other pumped storage facilities of similar
capacity are being planned. The pumped
storage at Sardar Sarovar (1200 MW) and Tehri
(1000MW) are planned for construction in near
future. In
Conclusion It is
intended to draw the attention of the
concerned Government agencies and various
institutions involved in Nepals water resources
development to great loss to the nation
if it is allowed to implement the 300 MW
Mini Upper Karnali Project. (Dr. Thapa
writes on water resources) |
|| Cover Story || Local Bodies || Politics || Indian Election || Interview || Suspension Of Support || Entertainment || Education || || Intellectulas || Book Review || Editor's Note || The Bottom Line || News Notes || Briefs || Quote Unquote || Off The Record || Letters || Opinion || Forum || Human Rights || |
Send your feedback to the
editor: spot@mail.com.np |